Updating Tasks in Microsoft Project 2010

5 pts.
Tags:
Microsoft Project 2010
Hi everybody, I have a question about MS Project. I have a task that starts on 16.04.2014 and finishes on 26.06.2014.
Start: 16.04.2014
Finish: 26.06.2014
Progress Data’s:
Actual start: 29.04.2014
Status Date: 29.06.2014
Completion: %60 (Actual Start till Status Date)
So in my opinion, I did %60 in 60 days, so I should work for 40 more days to complete task. The finish date should automatically change to “29.06.2014+40 days”.
There should be only one bar in gantt chart that shows completed task between actual-status date and not-completed task for 40 days. I tried all update tasks procedures but I couldn’t manage.
I just want to make this calculation automatically in MS Project.
What should I do? What are your recommendations?

Answer Wiki

Thanks. We'll let you know when a new response is added.
Send me notifications when members answer or reply to this question.

REGISTER or login:

Forgot Password?
By submitting you agree to receive email from TechTarget and its partners. If you reside outside of the United States, you consent to having your personal data transferred to and processed in the United States. Privacy

Discuss This Question:  

 
There was an error processing your information. Please try again later.
Thanks. We'll let you know when a new response is added.
Send me notifications when members answer or reply to this question.

REGISTER or login:

Forgot Password?
By submitting you agree to receive email from TechTarget and its partners. If you reside outside of the United States, you consent to having your personal data transferred to and processed in the United States. Privacy

Forgot Password

No problem! Submit your e-mail address below. We'll send you an e-mail containing your password.

Your password has been sent to:

To follow this tag...

There was an error processing your information. Please try again later.

REGISTER or login:

Forgot Password?
By submitting you agree to receive email from TechTarget and its partners. If you reside outside of the United States, you consent to having your personal data transferred to and processed in the United States. Privacy

Thanks! We'll email you when relevant content is added and updated.

Following