Task | Start Date | End Date | Predes.| Resource |Duration
------------------------------------------------------------------------
Task1 | 17-Aug-09 | 17-Aug-09 | | R1 | 1 Day
Task2 | 17-Aug-09 | 19-Aug-09 | 1SS | R2 | 3 Day
Task3 | 18-Aug-09 | 19-Aug-09| 1 | R1 | 2 Day
Task4 | 20-Aug-09 | 20-Aug-09| 3 | R2 | 1 Day
In this scenario when R1 completes task3 in 1 day then Task4 Start Date will change to 19-Aug-09. Where as actually R2 will be engaged from 17-Aug-09 to 19-Aug-09 in Task2. Which means R2 cannot work on 2 task simultaneously. How can I avoid such situation.
NB: All task type are created as Fixed Duration
Software/Hardware used:
MS Project
ASKED:
August 19, 2009 9:51 PM
UPDATED:
August 20, 2009 1:21 PM