TECO Project with pen Inventory reservations
Hi,Can you please help me with the solution that will stop closing Project using Transaction code CJ20N while the are still open inventory reservation that linked with the Project Inventory reservation
Answer Question
| May 8 2008 1:21 PM GMT
| asked by
SAP Project systems
SAP Project System, CJ20N, SAP PS
SAP-PS Estimating Offline
We need to do Job Estimating offline from SAP. Although the SAP -PS functionality looks like it would work, we must be able to estimate even without connectivity. SAP's work with Adobe sounds promising, using something like Flex would be ideal. Has anyone heard of someone either building or buying...
Answer Question
| Oct 31 2007 8:31 PM GMT
| asked by
Getmygto
SAP, SAP development, SAP A1S


