  • Microsoft Project start date

    Project 2007 - Software 1.  I have set a start date and have created an entire schedule, I now need to move the start date and keep the same sequences, but not all things are linked together - how do i do this? 2.  Multiple times this may occur throughtout the project. If my project is delayed by...

    ChipBroderick5 pointsBadges:
  • Why when I do traching to move all uncompleted work to the future is it changing a resources actual work?

    I am going to Tools - Tracking - Update Project -- I am updating the entire project and reschedule uncompleted work. I chose the date for the previous Sunday. This is a bran new plan so only 2 resources have coded hour to it, one of them was in a task alone and completed the task. There is a...

    ITtiffany5 pointsBadges:
  • MS Project Server errors

    I have Ms Project server 2007(S1), project pro(2007), SharePoint Server 2007(language pack [Turkish]installed on Server 2003 with MS SQL server 2005. I have only one farm. I can see when I create a project on server and client side. however whenever I want to see preview of a task, it gives an...

    Mahirkarabacak15 pointsBadges:
1

Forgot Password

No problem! Submit your e-mail address below. We'll send you an e-mail containing your password.

Your password has been sent to:

To follow this tag...

There was an error processing your information. Please try again later.

REGISTER or login:

Forgot Password?
By submitting you agree to receive email from TechTarget and its partners. If you reside outside of the United States, you consent to having your personal data transferred to and processed in the United States. Privacy

Thanks! We'll email you when relevant content is added and updated.

Following