What criteria would you use in selecting a life-cycle model for the Project?

You are a software engineering consultant and have been called in by the vice president for finance of a corporation that manufactures and sells boots. She wants your organization to build a product that will monitor the company’s stock, starting with the purchasing of the leather and keeping...

View Answer   |  Sep 17 2009  5:33 PM GMT
Life cycle management, IT project management
asked by Ashindya

  10 pts.

Responsibility of project delivery team

In the recessionary period what will be the added responsibility of delivery team towards their client?

asked by ITSeniorConsultant

  5 pts.

Career switch within IT from java and PM to SAP

I have 12 yrs of IT experience on java technologies and project management. Executed most of the project in the domain of SRM. based on that i want to make career in SAP MM. Could someone tell me how to proceed in this regard.

View Answer   |  Jul 8 2009  4:42 PM GMT
SAP MM, Careers, SAP careers
asked by Rags74

  5 pts.

Dependencies

what are the dependencies in a project? how can the project manager define the dependencies in the project?

View Answer   |  Jun 28 2009  12:59 AM GMT
IT project management, Project dependencies
asked by Weli

  15 pts.

detailed documented project

Can i have sample of a project with all its detailed documents related to the project management plan along with templates?

View Answer   |  Jun 15 2009  4:54 PM GMT
PM, Project management, IT project management
asked by Weli

  15 pts.

Best practices for approaching an IT Project

what is the approach of any project?, should it be in details?,what is the approach of Data entry project in telecom company?

asked by Weli

  15 pts.

What model of a lifecycle should IT projects follow?

In software development, one has the RUP, or the waterfall model for the application lifecycle. In my experience, IT projects differ widely from them, however, they rarely follow a set pattern of requirements sign-off, careful design, proper reviews and implementation after testing, documentation...

asked by Xafer

  5 pts.

Resource list with a gant chart showing task timelines

In project, I'd like a view of all resources with corresponding tasks under each resource. To the right of each task I want to see the calendar months with a gant chart type line depicting which months the resource will be working on that task. How do I create a view/report such as this? Do I...

View Answer   |  Mar 23 2009  7:07 PM GMT
IT project management
asked by Mpolitte

  15 pts.

IT projects

I am experienced QA lead with 10 years of experince.i left my hob and start a IT testing firm dedicated to testing projects. I am trying to find client project but not successful.Can anyone suggest what will the best approach?

View Answer   |  Feb 25 2009  11:37 PM GMT
Software Test Lead, QA testing, IT Job Market
asked by Amy009007

  5 pts.

Looking for study materials for PRINCE2

HI I NEED STUDY MATERIALS FOR PRINCE 2 CAN YOU HELP PLS HI CAN YOU SUGGEST ANYWEBSITE FOR STUDY MATERIAL AND PAST QUESTIONS HOW LONG WILL IT TAKE ME TO STUDY AND PASS THE EXAM

asked by Flow

  140 pts.

Building a Data Center from the ground up

In working with Construction PMs, what can an IT PM bring to the table for a project to build a data center from the ground up?

asked by Cybrown

  10 pts.

Bare minimum templates for Project Management

20 projects, 80 teams members, are engaged. for project management what will be the bare minimum templates required for best control of the projects. teams are scattered at various locations. can someone list the name of the templates required (for complete project management, and covering the...

asked by Jaideepkhanduja

  6375 pts.

PM training for Infrastructure structure and platforms

I'm a PM looking for training that will provide a good baseline on infrastructure platforms. Any recommendations for classes being offered that are not overly technical or hands on?

View Answer   |  May 5 2008  5:18 PM GMT
Training, Project Managers, IT project management
asked by Dekohls

  10 pts.

MS Project 07 Automated Communication

I am a project coordinator attempting to improve communications among resources assigned tasks in Project Server 2007. I would like to automate some of the issues and escalation of same - workflow type. What are the best tools for collaboration with this product? I'm semi new to MS Project and,...

asked by Sissy

  10 pts.

Project Metrics

Is there a different way to measure project status other than Schedule Performance Index (SPI) and Cost Performance Index (CPI)?

asked by 74

  0 pts.