Standard practice for servicing UPS in a data center

1110 pts.
Tags:
Data Center management
DataCenter
Fault tolerance
UPS
What do you do in a large datacenter environment that needs to have the UPS serviced? We are adding a second one for fault tolerance but will need to disconnect power for chunks of time. What is safe? What is standard practices?

Answer Wiki

Thanks. We'll let you know when a new response is added.

If your data center was properly designed, you will have a “maintenance bypass” which allows you to route power around the UPS if it’s offline for service without interrupting power to the floor.

In most cases, if you have a generator, you may want to run on generator power during the time the UPS is being serviced as the generator power is often cleaner and more reliable than that from the utility.

Start the generator beforehand and allow it to fully warm up. While the UPS is still functional, transfer the load to it and allow it to run that way for 15-30 minutes; if there are any problems, transfer back and cancel the maintenance. While the generator is suppling the load and before shutting down the UPS, check the readings (water, oil pressure, etc.) at the generator engine display and make sure they are all within normal range. And needless to say, check your fuel tank supply level!

If you don’t have a generator, watch the weather forecast and conditions closely. If bad weather is called for of present (especially T-storms or high winds), reschedule the maintenance for another day.

Discuss This Question: 4  Replies

 
There was an error processing your information. Please try again later.
Thanks. We'll let you know when a new response is added.
Send me notifications when members answer or reply to this question.

REGISTER or login:

Forgot Password?
By submitting you agree to receive email from TechTarget and its partners. If you reside outside of the United States, you consent to having your personal data transferred to and processed in the United States. Privacy
  • Batman47
    And if you don't have a generator you should rent one. I like the comment about checking the fuel supply level! Good point that our electric company failed to follow. They know better now since our servers crashed.
    1,050 pointsBadges:
    report
  • StevenG7
    A couple of other things I should add: (1) *Don't* -- under any conditions -- attempt to use the "UPS Maintenance Bypass wraparound breaker circuit on an operating UPS unless the UPS'es authorized service person has studied the "one-line" and says it's OK to do so! Engaging the wraparound bypass in effect shorts the output of the UPS back to the input, and may be catastrophic. There is a correct sequence to do this; your authorized service person should know this. (2) Discuss the MOPs (Methods of Operations & Procedures) with the authorized service person before doing the maintenance. Make sure you both understand exactly what will be done and the possible effects. You specifically said "UPS maintenance" as opposed to "repair". Most scheduled maintenance such as battery testing or replacements, inspections, etc., can be carried out using the UPS'es internal Static Bypass. While the load is not protected by the UPS during this procedure, it doesn't require use of the "wraparound bypass". Your authorized service person will know what needs to be done. (3) Due to new OSHA requirements regarding Arc Flash safety, operation of certain breakers (such as external maintenance wraparound ones) may now require proper Arc Flash protection, upto and including an arc-flash protective suit and operation only by trained personnel. These requirements are fairly recent so "I used to be able to do this myself" may not apply! Remember, as bad as an outage may be, it's nothing compared to an injury or death. Your authorized service person should have received training in the new OSHA regulations. Discuss this beforehand. In some cases, the operation of breakers required to switch the load to/from generators may now require an electrician or trained service personnel to do it.. (4) If you have generator backup and one or more ATS's, once again, be sure you understand how they really work! I saw a case were a operator used the ATS to start the generator and transfer the load, but the ATS said "hmmm.. the utility feed seems OK" and transferred the load back off the generator midway thru the UPS maintenance! Since the UPS was in bypass, this resulted in a brief power outage, enough to take down almost everything.
    480 pointsBadges:
    report
  • NewnanIT
    [...] Need pointers on standard practice for servicing UPS in a data center? Check out what StevenG7 and Batman47 had to say. 6. Carlosdl has a few ideas for how to get a [...]
    0 pointsBadges:
    report
  • NewnanIT
    [...] Standard practice for servicing UPS in a data center [...]
    0 pointsBadges:
    report

Forgot Password

No problem! Submit your e-mail address below. We'll send you an e-mail containing your password.

Your password has been sent to:

To follow this tag...

There was an error processing your information. Please try again later.

REGISTER or login:

Forgot Password?
By submitting you agree to receive email from TechTarget and its partners. If you reside outside of the United States, you consent to having your personal data transferred to and processed in the United States. Privacy

Thanks! We'll email you when relevant content is added and updated.

Following