In the material master we currently use a planning calendar in conjunction with a period-planning lot-size to plan for procurement. This does not help us indicate a planning/ordering date, only a delivery date.
Can I use the planning cycle to tip-off ATP to what our ordering deadline is? If so what configuration is necessary? Correct me if I'm wrong, but I think I need a time-phased planning lot-size to make this work?
Regards.
Software/Hardware used:
ASKED:
May 12, 2004 12:57 PM
UPDATED:
May 13, 2004 11:06 AM
This will not work for us, consider this example:
If a purchase order for material A is placed on Friday and delivered the next Friday, that is a lead time of 7 days. But if I create a sales order on Tuesday, I can’t get the material in 7 days, the material won’t even have a purchase order placed until Friday.
I’ve heard of this to be called the “leap-frog” effect. I know that the solution involves time-phased planning, and utilizing the planning cycle, but I just can’t get it to work.