I've got two *immed PTF's to apply, but one of these has a delayed pre-req PTF and the pre-req PTF also has a delayed pre-req PTF.

If I set the two delayed pre-req PTF's to apply at the next IPL, will the system apply them in the correct order? Or is it best to do one at a time?



Software/Hardware used:
AS/400

Answer Wiki

Thanks. We'll let you know when a new response is added.

Except for very rare cases, the delayed PTF’s can all be applied at the same time, and the system will handle the sequence.

Discuss This Question: 1  Reply

 
There was an error processing your information. Please try again later.
Thanks. We'll let you know when a new response is added.
Send me notifications when members answer or reply to this question.
  • WoodEngineer
    Recommend setting all the PTFs you need to apply as delayed. This will minimize problems.
    6,955 pointsBadges:
    report

Forgot Password

No problem! Submit your e-mail address below. We'll send you an e-mail containing your password.

Your password has been sent to:

To follow this tag...

There was an error processing your information. Please try again later.

Thanks! We'll email you when relevant content is added and updated.

Following

Share this item with your network: