Follow this simple steps to set the dates….
1. Go to Tools > Change Working Time
2. Select the column header for Monday and Saturday
3. Now set the option for non-default working time
4. U probably also should change the hours per week setting under Tools/Options/Calendar tab to be 56, assuming you are using a standard 8 hour working day. (Optional)

Discuss This Question: 2  Replies

 
There was an error processing your information. Please try again later.
Thanks. We'll let you know when a new response is added.
Send me notifications when members answer or reply to this question.

Forgot Password

No problem! Submit your e-mail address below. We'll send you an e-mail containing your password.

Your password has been sent to:

To follow this tag...

There was an error processing your information. Please try again later.

Thanks! We'll email you when relevant content is added and updated.

Following

Share this item with your network: