5 pts.
 MS Project 2007 - Working days
I want to set my working days to be mon-sat (6 days a week) in MS project 2007.  I am lost lost lost

Software/Hardware used:
MS Project 2007
ASKED: Sep 7, 2010  4:00 AM GMT
UPDATED: November 25, 2010  10:56:57 AM GMT
20,980 pts.

Answer Wiki:
Follow this simple steps to set the dates....
1. Go to Tools > Change Working Time
2. Select the column header for Monday and Saturday
3. Now set the option for non-default working time
4. U probably also should change the hours per week setting under Tools/Options/Calendar tab to be 56, assuming you are using a standard 8 hour working day. (Optional)
Last Wiki Answer Submitted:  Nov 25, 2010  10:56 AM (GMT)  by  Rechil   20,980 pts.
To see other answers submitted to the Answer Wiki View Answer History.