5 pts.
 Job Scheduling in AS/400
How do I schedule a job in AS400?

Software/Hardware used:
ASKED: January 13, 2009  4:38 AM
UPDATED: January 14, 2009  11:19 PM

Answer Wiki:
I think the comple command is ADDJOBSCDE. Regards Hector ADDJOBJS - Add job using Job schjeduler Using this command, we can schedule the job
Last Wiki Answer Submitted:  January 14, 2009  4:44 am  by  rajeshece   1,040 pts.
All Answer Wiki Contributors:  rajeshece   1,040 pts.
To see all answers submitted to the Answer Wiki: View Answer History.


Discuss This Question:
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _


 

Hi,

You can also use WRKJOBSCDE to work with and add scheduled jobs.

Regards,

Martin Gilbert.

 23,625 pts.

 

GO JS
Will get you to the Advanced Job Scheduler if you have it installed.
Much better design and functionality than the other one.