16,755 pts.
 Hyper-V and VMware budget planning
I am looking at 'management costs' associated with Hyper-V...VMWare has Virtual Center for a fixed rate. With 12-15 servers what would I need to budget for this with MS? This question is from the 5/14 Microsoft Virtualization Chat on ITKnowledgeExchange.com

Software/Hardware used:
ASKED: June 18, 2009  1:51 PM
UPDATED: June 18, 2009  2:28 PM

Answer Wiki:
VMware charges a fixed cost for vCenter but a per host charge for ESX. Microsoft charges per host for System Center Suite but the cost is still 1/5 that of buying VI3/ESX. Thus, the cost savings still scale accordingly.
Last Wiki Answer Submitted:  June 18, 2009  2:23 pm  by  EdwinYuen   3,730 pts.
All Answer Wiki Contributors:  EdwinYuen   3,730 pts.
To see all answers submitted to the Answer Wiki: View Answer History.