Hello..would like to know what are the steps for a disaster recovery exercise on as400?

Software/Hardware used:
as400, iseries

Answer Wiki

Thanks. We'll let you know when a new response is added.

The company must determine how long they can be without the computer. Then you can start developing a plan.

For instance, If they can only be down for minutes, they you need to be replicating your data on another machine. If days, then you need to make sure you have access to another machine to load data from your backups.

What to do if machine is OK, but building is destroyed.

Etc. A disaster plan can takes a long period of time to develop.

Then you need to test it.

You will need to do plenty of research (or hire someone who is experienced in this to assist or do it for you) 

Discuss This Question: 4  Replies

 
There was an error processing your information. Please try again later.
Thanks. We'll let you know when a new response is added.
Send me notifications when members answer or reply to this question.

REGISTER or login:

Forgot Password?
By submitting you agree to receive email from TechTarget and its partners. If you reside outside of the United States, you consent to having your personal data transferred to and processed in the United States. Privacy
  • TomLiotta
    You need to tell us almost everything about your system before we can tell you what a useful disaster recovery exercise would be. We need to know hardware components, software components, networking requirements, business requirements, types of workload, and more. We need to know what equipment you have available to act as your recovery site. And we need to know what your recovery requirements are -- what priorities are for getting which system elements working and when. -- Tom
    125,585 pointsBadges:
    report
  • jinteik
    It also depends a lot on the type of business you do
    17,330 pointsBadges:
    report
  • TomLiotta
    My all-time favorite DR exercise scenario starts with the CEO showing up early, locking the data center and telling everyone who shows up that the data center is off-limits for the day. A 'disaster' has happened and everything on the other side of the door is 'destroyed'.   The work for the day is to get the DR site up and running.   How many would make it through?   Tom
    125,585 pointsBadges:
    report
  • ToddN2000
    All I can say from personal experience is get one in place and quick. Many years back (1987?) I was working as a night operator/programmer. There was a bad storm going on outside and I call the manager and asked if I should hold off on the IPL. He said no go ahead and do it. Well as the system was coming back up we took a power hit. We did not have a UPS on this s/38, and BOOM it crashed . When the power came back we tried to bring the system back but were out of luck. The drive that held the micro-code and address info was damaged. After IBM installed a new drive, we had to recover the system from tapes. Well they weren't as current as we thought because we limped by for about 2 weeks before we finally got our system back and fully functional. Prepare a DR as soon as you can.
    7,855 pointsBadges:
    report

Forgot Password

No problem! Submit your e-mail address below. We'll send you an e-mail containing your password.

Your password has been sent to:

To follow this tag...

There was an error processing your information. Please try again later.

REGISTER or login:

Forgot Password?
By submitting you agree to receive email from TechTarget and its partners. If you reside outside of the United States, you consent to having your personal data transferred to and processed in the United States. Privacy

Thanks! We'll email you when relevant content is added and updated.

Following