Question

  Asked: Feb 18 2008   4:29 AM GMT
  Asked by: Maxx47


Data Cener consulting


Green data center, Data center design

We are planning to build a tier IV data center and seeking professional help assist us
to plan a green data center. please mail us scope of services and costs

Subscribe to Alerts! Get questions and answers delivered to your Inbox.


E-mail me updates on this question



   SUBSCRIBE

hidden modal window

Answer Wiki (Improve, edit or add to this answer)


 RATE THIS ANSWER
0
Click to Vote:
  •   0
  •  0



Over the data center traditional costs for design and construction, if you go green the costs will be impacted around 2.75%- 4.0% of the cost of work.

West of Texas , design build is used as approach for design and construction. This minimizes the overall cost of the project and provides for a faster delivery.

East of Texas, basically the approach is Design/Bid/Build.

Currently the costs for Tier IV at the planning stage are around $ 11,000 to $12,000 per kW ( IT Consumption), or regular terms around $1500-2000 per raised floor square foot.
  • AddThis Social Bookmark Button

Browse more Questions and Answers on DataCenter.