Question

  Asked: Jul 15 2005   9:28 AM GMT
  Asked by: joycesvp


Creating material with Automatic PO


SAP, MySAP, mySAP Supplier Relationship Management, R/3, SAP development

I need to create purchase requisition from sales order. In the material master, it is required that 'Automatic PO' be checked, right ? If this is checked and the material is used for regular purchase order (no requisition), would the material be applicable to both scenario ? I do not use MRP. On version 46B.
Any comments, pls ? Thank you in advance.

Subscribe to Alerts! Get questions and answers delivered to your Inbox.


E-mail me updates on this question



   SUBSCRIBE

hidden modal window

Answer Wiki (Improve, edit or add to this answer)


 RATE THIS ANSWER
0
Click to Vote:
  •   0
  •  0



It is not necessary to check the "Automatic PO" in the material master. The settings you're looking for are in the configuration of the schedule line category for the sales document item. In the schedule line config, you can assign an "order type" which is basically the purchase requisition document type that will be created from the sales order schedule line quantity.
  • AddThis Social Bookmark Button

Browse more Questions and Answers on SAP.

Looking for relevant SAP Whitepapers? Visit the SearchSAP.com Research Library.


Discuss This Answer


You must be logged-in to discuss a question. Log-in/Register