The availability check that occurs when a production order is released checks the current and future requirements. This is causing a problem; even though there is enough materials on hand to cover the production order being released we still get an availability check because there isn’t enough material to cover future requirements. Is there a way to limit the check to only include requirements through the date of the production order that is being released?
Software/Hardware used:
ASKED:
June 2, 2009 1:02 PM
UPDATED:
June 2, 2009 1:21 PM