Jul 2 2009   1:14AM GMT

NSA to build massive $1.6 billion data center in Utah



Posted by: Mark Fontecchio
Data center construction, mega data center

Last week President Barack Obama signed a war spending bill that, among other things, gets the ball rolling on a massive National Security Agency data center that is estimated to cost $1.6 billion over the next four years.

The data center would be built at Camp Williams, a military base just south of Salt Lake City. The 200-acre data center site would have 65 megawatts of total electric load, which is about the same amount of power used by all the homes in Salt Lake City. About 30 megawatts of that total would be for the IT load, according to military documents, with room to expand up to 65 megawatts. According to government records:

Installed infrastructure will support 65MW technical load data center capacity for future expandability. The design is to be capable of Tier 3 reliability. Power density will be appropriate for current state-of-the- art high-performance computing devices and associated hardware architecture.

Congress last week passed and Obama signed the bill authorizing the start of the NSA data center construction, with initial spending approval for $169.5 million. The agency hopes to begin construction of the facility in September and finish by next May. Some other details from the project:

REQUIREMENT: This project is required to provide a 30MW technical load data center and infrastructure for 65MW technical load data center capacity to support mission. The project will include the following:

Site

  • Facility design goal will be to the highest LEED standard attainable within available resources and will include: sustainable site characteristics, water and energy efficiency, materials and resources criteria, and indoor environmental quality.
  • Mechanical and electrical plants are to be housed in separate structures to prevent transfer of noise and vibrations to the data centers

Facilities

  • Data center technical load of 30 MW distributed across raised floor are the design parameters for the facility.
  • The infrastructure support and administrative areas will be designed to support state-of-the-art high-performance computing devices and associated hardware architecture.
  • Slab floor loading of approximately 1500 pounds per square foot (PSF)
  • Enhancements to the building for IT and security include construction as a sensitive compartmented information facility (SCIF), as well as, requirements related to Antiterrorism Force Protection (ATFP).

Structural

  • Technical load will be distributed across the data center areas.
  • Seismic considerations are to be made in the facility design.
  • Data center areas are to have depressed concrete slab construction with a load bearing capacity of 1500 pounds per square foot (PSF).
  • Facility command and control contained in a central modular office component.
  • Facility will have a loading dock with vehicle bays, three (3) of which are to be equipped with dock levelers sized to handle tractor trailers.

Electrical

  • Technical load capacity is 30 MW with loads distributed evenly across the data center areas.
  • Supervisory Control and Data Acquisition (SCADA) to either PDU level or distribution panel level if required
  • Dedicated substation for each critical UPS.
  • UPS and generator backup for facility systems.
  • Generators will include Selective Catalytic Reduction (SCR) pollution control equipment, chemical storage tanks and feed system.

Mechanical

  • Chilled water system to support both air and water cooled equipment.
  • Each data center area is to have air cooled and water cooled equipment with Computer Room Air Handlers (CRAHs) located external to the raised floor area. The piping headers / systems are to be designed to accommodate future expansion.
  • Back-up capability for mechanical equipment.
  • Cooling Towers
  • Air distribution redundancy for CRAHs.
  • Fire Protection - Double interlocked pre-action fire protection system for all electrical and mechanical support spaces.
  • Wet pipe for administrative and raised floor areas per DOD standards.

Security systems

  • Video surveillance
  • Intrusion detection
  • Access control system

Jun 29 2009   1:15PM GMT

Apple to reportedly build $1 billion data center in Maiden, N.C.



Posted by: Mark Fontecchio
Data center construction

Apple will reportedly build its huge new East Coast data center in Maiden, N.C., according to local media and Data Center Knowledge.

According to the reports, the facility will be built in Maiden, N.C., a small town of about 3,300 people in the western part of the state, about an hour north of Charlotte. The $1 billion price tag is supposedly what Apple’s investment will be over the course of nine years, and the facility is expected to employ at least 50 full-time employees. The North Carolina Department of Commerce estimates that the data center will create more than 3,000 jobs total, many of them related to facility construction.


May 26 2009   6:11PM GMT

The $1 billion data center?



Posted by: Mark Fontecchio
Data center construction

Data Center Knowledge cites local media reports on speculation that Apple is building a massive data center that could cost as much as $1 billion.

Most of the massive data centers out there from Microsoft and Google have price tags around $500 million, so $1 billion would be a big jump. What makes the cost so high? Who knows. If it happens, this thing is likely to be monstrously large.